“Municipal and Housing Affairs” Outlines Requirements for Issuing Excavation Permits via the Baladi Platform

The regulations specify the conditions for approval and supervision, as well as the deadlines for issuing excavation permits: 30 days for highways and 60 days for other roads.

Ministry of Municipalities and Housing - Group Housing Requirements

Posted in

His Excellency Majid bin Abdullah Al-Hogail, Minister of Municipal, Rural Affairs, and Housing, approved the Regulations on Excavation Permits, which aim to coordinate public utility services for the issuance of excavation permits within the urban areas of the Kingdom’s cities and provinces, through the “Nassiq” service, which allows the entity requesting the permit to coordinate with the relevant authorities to issue excavation permits via the Baladi platform.

Conditions for Issuing Excavation Permits

The regulations include a number of conditions for issuing excavation permits through the Project Coordination Office in municipalities; most notably the submission of a license application and adherence to quality assurance standards, in addition to compliance with the technical requirements specified by the Ministry, including adherence to the timeframes and the specified route length for the licenses, and the applicant’s commitment to the coordination arrangements made with the relevant authorities.

30 days for excavation permits for highways and 60 days for other roads

The regulations specify 30 days for permits for general excavation work on highways and 60 days for other roads, as well as main, secondary, and local streets, It also specifies 150 days for highway construction permits and 300 days for permits for main and secondary streets; the municipality may extend the permit period, provided that the extension does not exceed the project’s implementation period.
The regulations require the entity applying for the permit to engage an accredited consulting firm and obtain approval from the relevant authorities for the permit, The applicant must pay any outstanding municipal fines within 60 days and submit a traffic plan (approved by traffic authorities) in the event of a street closure or a change in traffic flow.

The Ministry has called on all beneficiaries and relevant parties to review the new regulations for excavation permits by visiting the link https://momrah.gov.sa/ar/regulations?type=221.

It should be noted that “Nassiq” is a unified electronic service provided through the Baladi platform to carry out various services related to excavation work, such as coordinating excavation activities and issuing, extending, and revoking excavation permits for entities requesting them, with the aim of avoiding any damage, obstacles, or duplication that may result from the excavation process—a prerequisite for issuing permits.