As part of the advanced implementation stages of the road network development project surrounding King Abdullah Financial Center (KAFD), whose completion rate exceeded 35%, Royal Commission for Riyadh City carried out a precise engineering lifting and installation of two flyovers using specialized cranes and equipment, as part of the ongoing construction work to develop one of the most vital axes in the north of Riyadh.<The lifting work was carried out according to an integrated operational and traffic plan, taking into account the maintenance of traffic flow and the safety of road users, with field coordination between engineering, operational and traffic teams, in addition to the application of safety standards and technical procedures adopted at all stages of implementation. The project to develop the road network surrounding King Abdullah Financial Center extends for more than 20 kilometers, and includes the implementation of 3 major intersections and 19 bridges; to enhance traffic efficiency, improve access to King Abdullah Financial Center, and raise the level of connectivity between the main axes in northern Riyadh, in line with urban and economic growth
Precision-engineered lifting and installation of bridges around King Abdullah Financial Center
The project includes the development of more than 20 kilometers of roads and 19 bridges to improve traffic flow and enhance the connectivity of northern Riyadh