Property Articles Home of a Lifetime Step by step By Majid Almuhaimeed

Posted in

The electrical boxes are installed when they are finished. The metal box for the sub-distribution panels (“distribution boards”) is supplied. Only the box is installed, while the cover and the circuit breaker are kept until they are installed during the final finishing. The location of the electrical distribution panels (“distribution boards”) for each floor is predetermined during the “structural” stage, and it is absolutely not recommended to change the location of the distribution board, as this would entail a lot of effort, material costs, and changing the path of the cable and wires.

The type of exhaust fans for bathrooms is determined. It is preferable to use ceiling fans that are installed within false ceilings. There are fans that are installed directly on the wall or window, and the former is the best. Regarding kitchens, it is recommended to install fans that are installed above the oven, which require the installation of a duct. This type of fan is suitable for the amount of odors and oils produced in the kitchen environment and is recommended.

The electrician installs the splitters as needed. The use of wooden splitters is not recommended at all. We can use splitters made of galvanized iron or plastic. The "service box" made of galvanized iron and equipped with side openings is available in the market, in addition to a door that can be opened and closed when needed. It is recommended to install it outside the building in places exposed to weather conditions.

It is recommended to establish a conduit for the future passage of the fiber optic internet cable. The conduit is established from the outer wall of the building to the inside of the building next to the central office. The conduit is a flexible 1-inch cable, and a rope is placed inside the conduit to later pull the cable through it. The conduit must be straight and free of breakage. It is recommended to establish internet points in all spaces in the building. Establishing internet points in all spaces of the building does not eliminate the need to establish telephone points (central office) in all rooms and halls.

Upon completion of these works and implementation of the required installation for all electrical points, the order for electrical wires is registered. Wires are available in the market and are of two types:

First: According to American specifications

Second: According to English specifications

It is preferable to use American-specification wires manufactured by leading companies in this field to ensure the purity of the copper and the ease of stripping, which helps save time for the electrician during the drawing process. They are also highly flexible, which makes them non-cracking, allowing for easy drawing inside pipes. Additionally, the variety of available colors helps the electrician and the owner distinguish electrical lines without difficulty or complication. Note that the price of American-specification wires will be higher due to their superior insulation specifications and the length available on the reel.

Choosing the right time to pull the wires is done according to the project specifications, and in coordination with the electrical engineer, according to the method he is proficient in implementing, and not forcing him to use a method he is not proficient in implementing perfectly, which may cause errors in implementation due to the electrician's lack of skill in this method. The wires in the building can be pulled in two stages:

First stage: Pulling the wires before plastering:

If the building's electrical boxes were installed in the ceilings during the "skeleton" stage, then upon completion of the installation of electrical boxes for sockets, switches, and distribution panels ("distribution boards") inside the building, and before starting the plastering work, the electrician can pull all the wires during this stage.

Second stage: Pulling the wires after plastering:

If the electrical wiring is underground, boxes for sockets, switches and distribution boards (“distribution boards”) are installed inside the building, with the necessary covers made before plastering, and the wires are pulled later when the plastering work is completed.