“City Housing” discusses the services of 594 residential plots in Yanbu

Posted in

The Ministry of Housing Medina Branch revealed that the housing project in Yanbu Al-Bahr contains 594 pieces and the implementation period for the project is 18 months, and Yanbu Governor Engineer Musaed Al-Salim emphasized on all competent authorities to quickly develop an action plan to deliver services from water, electricity and communications once the infrastructure of the project is completed.

The meeting discussed the approval of the plans and materials by the electricity company, and the lack of implementation of the electrical feed to the site facilities. The meeting also discussed the approval of the plans and materials by the Electricity Company, the lack of implementation of the electrical feed for the site facilities, the issue of the presence of a medium voltage power cable specified in the southwest corner of the project, and the lack of a feeder for the telecommunications network in front of the northern facade of the project (the main street), and emphasized the need to implement it in front of the project facade to take a sub-network for the project.

The meeting stressed the need to implement it in front of the project facade to take a sub-network for the project.