The meeting discussed the approval of the plans and materials by the electricity company, and the lack of implementation of the electrical feed to the site facilities. The meeting also discussed the approval of the plans and materials by the Electricity Company, the lack of implementation of the electrical feed for the site facilities, the issue of the presence of a medium voltage power cable specified in the southwest corner of the project, and the lack of a feeder for the telecommunications network in front of the northern facade of the project (the main street), and emphasized the need to implement it in front of the project facade to take a sub-network for the project.
The meeting stressed the need to implement it in front of the project facade to take a sub-network for the project.